Construction work started

Construction work started at 05.09.2012

Then the time had come: Construction work on our new factory building with almost 1,900sqm of floor space began on 5 September 2012. It was a long and difficult way from applying for a building permit in mid-February 2012 to its granting in mid-August 2012. Initially, this new building was not included in any development plan, and later it turned out that the property to be built on was situated in a conservation area. These conditions are anything but good for obtaining such building permit. In the end, however, it has been possible because both the municipality and Planungsbüro Schubert, a company based in Radeberg, joined forces and worked towards the same goal.